Invinity Energy Systems has confirmed the three locations where it will deploy 43MWh of vanadium flow batteries for Dairyland Power Cooperative, turning a supply agreement first announced on 3 August into a sited, scheduled build across the US Upper Midwest.

Frentress Lake and Alma

According to the project update published on 18 November, one battery system will be built at Frentress Lake, Illinois, where the local distribution cooperative is JCE Co-op. The remaining two systems will be installed at Dairyland's Alma site in Alma, Wisconsin, served by Riverland Energy Cooperative. Together the three installations account for the full 43MWh order.

The batteries will be Invinity's Endurium vanadium flow platform, manufactured in the United States, with deliveries expected to begin at the end of 2027. That places construction and commissioning in 2028 — a reminder that flow battery projects move on utility procurement and interconnection clocks rather than factory clocks.

Why a cooperative bought long duration

Dairyland, founded in 1941, supplies wholesale power to 24 Class A member distribution cooperatives, two Class B members and 27 municipal utilities, serving more than 800,000 people across a 44,500 square mile territory and 3,700 miles of transmission line. That footprint is rural, weather-exposed and often transmission-constrained — the profile that has made cooperatives early adopters of storage lasting materially longer than lithium-ion's typical two to four hours.

Utilities need storage that can respond to changing grid demands, whether on the scale of hours or milliseconds, and operate reliably over a decades-long operating life. — Matt Harper, President, Invinity Energy Systems

Invinity positions the technology around heavy-duty cycling: unlimited cycles, a 30-year-plus operating life and a non-flammable electrolyte. For a member-owned utility, the pitch is less about energy arbitrage than about avoiding repeat replacement costs on assets financed over decades.

What to watch next

The milestones that matter now are binding delivery schedules for US-manufactured Endurium units, site permitting at Frentress Lake and Alma, and interconnection timing with the two local cooperatives. Invinity has also said it targets a 66 percent product-cost reduction on Endurium deliveries in 2027 — a claim that will be tested precisely as these first US-built units ship.

This article was assisted by AI analysis. Please refer to the original source for official information.