New York's energy storage procurement is opening a new route for non-lithium technologies. On 12 November 2026, NYSERDA announced a second bulk energy storage solicitation seeking projects that could add 1,000 MW of battery storage across New York by 2030.

The solicitation is part of Gov. Kathy Hochul's plan for 6,000 MW of battery storage by 2030. The first round of awards announced in summer 2026 included two of eight new projects for Long Island, in Holtsville and Manorville.

Longer contracts for non-lithium

Non-lithium battery proposals are eligible for 25-year contracts, versus 15-year contracts for lithium-ion proposals. NY Green Bank will offer a range of financing options, and NYSERDA's siting team will provide education and model local laws to municipalities.

Contract terms

The contract structure is significant for flow batteries and other LDES technologies because longer revenue certainty can improve bankability for projects with higher upfront costs but long operating lives.

Developer interest on Long Island

Larry Siegel, a Wantagh businessman with an energy finance background and former U.S. Department of Energy employee, is in early-stage development of a 5 MW non-lithium flow battery storage project for eastern Long Island through his newly formed company Tobay Energy. The site is less than an acre, he has met with PSEG Long Island about grid interconnection, and the project could be ready by 2028. He is still finalizing design and manufacturer selection, with costs depending on interconnection.

Flow batteries use liquid electrolytes rather than solid lithium-ion cells, relying on zinc-bromine or vanadium chemistries to store power for up to four hours of discharge onto the grid. Siegel said flow batteries are not subject to the thermal runaway fires associated with lithium batteries and are already in use in New York State and across the country.

Local siting remains a hurdle

Nearly all Long Island towns have moratoriums on battery storage. Islip Town recently approved a ban on batteries over a certain size that could scuttle a LIPA contract for a 79 MW battery. Brookhaven has a special zone for batteries and no moratorium, but Supervisor Dan Panico has said nothing will be approved until the town is sure projects are safe.

Siegel said demand for many such batteries exists across Long Island but moratoriums make construction very difficult.

LIPA said it welcomes NYSERDA's efforts to advance storage innovation and help promising technologies become commercially viable. The need is growing as LIPA prepares to accommodate up to 924 MW of wind energy early next year.

This article was assisted by AI analysis. Please refer to the original source for official information.