Two policy moves in late 2026 have sharpened the public toolkit for long-duration energy storage on opposite sides of the world — one built on grants, the other on revenue certainty.
New York: USD 13 million across 15 projects
In November 2026, the New York State Energy Research and Development Authority (NYSERDA) awarded nearly USD 13 million to 15 energy storage innovation projects supporting advanced long-duration energy storage and next-generation battery technologies. The selected portfolio spans iron-sodium batteries, advanced compressed-air energy storage, zinc-manganese dioxide batteries and metal-air storage systems, with several projects targeting storage durations exceeding 10 hours.
The spread of chemistries is the point. Rather than picking a single winner, New York is funding a portfolio that hedges across electrochemical, mechanical and metal-air pathways — an approach that de-risks the state's longer-term storage build while keeping early-stage developers alive through the valley of death between laboratory results and bankable projects.
Japan: eligibility rules for the FY2026 auction
In September 2026, Japan's Ministry of Economy, Trade and Industry (METI) introduced updated eligibility guidelines for its FY2026 Long-Term Decarbonized Power Source Auction. The revised framework explicitly includes long-duration energy storage technologies such as mechanical, thermal and chemical storage. Eligible projects are generally required to provide at least 30 MW and six hours of continuous operation, and the mechanism provides long-term revenue support intended to encourage investment in large-scale energy storage infrastructure.
New York: nearly USD 13 million to 15 projects. Japan: eligibility generally requires at least 30 MW and six hours of continuous operation, backed by long-term revenue support.
Two different levers
The contrast is instructive. NYSERDA's grants fund technology demonstration — they lower the cost of proving a concept. Japan's auction funds deployment economics — it lowers the cost of capital for assets that already work, by guaranteeing revenue over a long horizon. A mature LDES market needs both: something to get chemistries through first-of-a-kind installations, and something to make the tenth installation financeable.
The 30 MW and six-hour thresholds in Japan also send a clear signal about what counts as long duration in procurement terms. Six hours is well beyond the four-hour default of most lithium-ion tenders, and it aligns with the durations NYSERDA's awardees are chasing. For developers, the practical read-across is that public support is increasingly conditioned on duration, not just megawatts.
This article was assisted by AI analysis. Please refer to the original source for official information.